Resurfacing works will take place in Garvald between the above dates, weather permitting. The road will be closed to traffic during working hours.
Phase 1 – Western Extent to Burnside Court – Monday 11th to Friday 22nd November
Phase 2 – Burnside Court to Eastern Extent – Monday 25th to Friday 29th November
Cones will be placed in advance, in the relevant area for each phase of the work, and locals are kindly asked to adhere to the restrictions. Diversions will be in place. Parking will also be restricted in the area of Linden Cottage, on the C104, to facilitate the diversions and vehicles turning.
Emergency vehicle access will remain and refuse and recycling will continue to be collected.
For further details on the phases of the work and the areas affected, please see the following link: tellmescotland